Service 05 · Design, permits and construction

Design and construction: from concept to keys, on the client’s side

We select a licensed consultant and main contractor, obtain all permits and supervise construction on your behalf: budget, schedule, quality and safety.

4–9 mo.design and permits
12–36 mo.construction through handover
1,5–3%client representative fee as a share of construction budget
Why it matters

Why you can’t just “bring your own team” here

Design and construction in Dubai are licensed activities. The engineering consultant handles submissions to Dubai Municipality, and the main contractor must hold a category matching the project’s scale, a staff of registered engineers and an HSE system.

Local crews and contractors are usually more cost-effective than bringing your own: they know the Dubai Building Code, suppliers and the approval process. Our job is to choose the right ones and supervise them.

Before signing a contract, we check not only the contractor’s DET licence but also its permitted activities, category, engineer registrations, access to the Dubai Building Permit System, insurance and project history.
What’s included

Scope of work

01Design

  • Selecting an engineering consultant
  • Concept and architecture
  • Detailed design and BOQ
  • Value engineering without compromising the product

02Permits

  • Building permit from Dubai Municipality
  • Power and water — DEWA
  • Civil Defence, telecom, district cooling
  • Master developer NOC and design guidelines
  • Completion certificate

03Construction

  • Tender and main contractor vetting
  • Schedule, budget, change orders
  • Site supervision, quality control, HSE
  • Escrow tranches by progress
  • Acceptance, snagging and handover
How it works

Stages and timeline

Timelines are indicative: the exact schedule is fixed in the contract after the strategy session.

  1. Consultant

    Selection of and contract with an engineering consultant.

    2–4 weeks
  2. Design

    Concept, detailed design, BOQ.

    3–6 mo.
  3. Permits

    DM, DEWA, Civil Defence, NOC.

    2–4 mo.
  4. Tender

    Prequalification and selection of the general contractor.

    1–2 mo.
  5. Construction

    Oversight through to completion and handover.

    12–36 mo.
Result

What you get

  • Agreement with a licensed consultant
  • Detailed design and BOQ
  • Building permit and utility approvals
  • General contractor agreement with performance security
  • Monthly reports on budget, schedule and quality
  • Completion certificate and handover
Who is responsible for what

Roles and licences

Clear division of roles

We we act as the client’s representative: selecting participants, controlling budget, schedule and quality, and reporting to the owner.

Design and submissions are handled by a licensed engineering consultant; construction by a licensed general contractor. Permits are issued by Dubai Municipality, DEWA, Civil Defence and the master developer.

Price

What it costs

Indicative pricing. The exact price is fixed in the estimate after the strategy session or Entry Blueprint.

ServiceWhat’s includedPrice
Budget and tenderCost plan, BOQ, tender and contractor vettingfrom $15,000
Permits and approvalsBuilding permit, DEWA, Civil Defence, NOCfrom $25,000 by stage
Client’s representativeSite supervision, HSE, acceptance and handover1.5–3% of the construction budget

Prices exclude 5% VAT, government fees and the services of licensed lawyers, consultants and contractors, which are paid under their own contracts. We do not guarantee decisions by banks or government authorities — we prepare the project so that risks are known in advance.

FAQ

FAQ

Didn’t find your answer? Ask at the strategy session.

A benchmark for mid-rise residential is around AED 450–700 per sq ft excluding land, depending on class and finishes. An exact figure comes from a cost estimate for the specific project.

The concept, yes, but the detailed design must comply with the Dubai Building Code and be submitted by a licensed local consultant.

Buyers’ funds are held in escrow and released against verified progress. We reconcile the contractor’s progress certificates with actual work completed.

For a first project, usually not: it means a licence, a team of engineers and ongoing compliance. Your own company makes sense once you have a steady pipeline of projects.

Let’s discuss your project in Dubai

Strategy session: 2–3 hours with experts, a review of budget, segment and entry route. $1,500 is credited towards the Entry Blueprint.